Tomislav Jureković HERALPJ Issue 162, 21 December 2015

The HERA announced a public consultation on the electricity transmission system ten-year plan proposed by the Croatian Transmission System Operator (HOPS). The plan covers the 2016-2026 period, with detailed elaboration of an initial three-year and one-year period.

By 2026, the HOPS plans to invest €684 million of its own capital. In addition, €16.8 million is planned to be obtained from the Connecting Europe Facility Fund (CEF) for the joint projects of smart grids that were included into the Project of Common Interest List (PCI), in cooperation with Slovenia. A public consultation is open until 26 December 2015.